Integrated System Plan

Share Integrated System Plan on Facebook Share Integrated System Plan on X (formerly Twitter) Share Integrated System Plan on Linkedin Email Integrated System Plan link

OPPD's Integrated System Plan (ISP) is a vital step in our continual planning process to guide us as we make long-term system plans.

Like most utilities, OPPD engages in ongoing system planning, with an intentional focus on publishing an update to our resource and system strategies every five years. The update also meets a regulatory requirement set by Western Area Power Administration (WAPA) as part of a long-term contract to receive hydroelectric power.

In early 2026, OPPD will begin its ISP engagement process, with a final report submitted to WAPA by the end of the year. This planning process is important to ensure we are ready to support growth and maintain reliability for our customer-owners and the ISP guides how we optimize our energy portfolio and measure potential additions over time.

The last time we submitted an Integrated Resource Plan to WAPA was in 2021. The planning process will differ slightly this time because OPPD will take a broader look at overall system needs, rather than just resource needs. This expanded view will allow OPPD to evaluate generation options in conjunction with related grid infrastructure and customer solutions, including the cost of potential grid buildout and modernizations and other factors in evaluating long-term options.

Long-term, taking an integrated systems approach to planning may uncover grid or customer solutions that can help with generation needs and vice versa which will help optimize the overall planning process.

The study also looks at how our resources actually are being used. In addition to traditional models that forecast the economic dispatch of generating units on the basis of cost only, a system plan will consider the current and future generation required for grid support and system reliability. This creates a modeled portfolio that performs much closer to real-world operations and captures the full range of costs and values.

Workshop #1 - March 24

To view the workshop 1 recording, click here.

To view the workshop 1 executive summary, click here.

We accepted feedback through April 23.

Workshop #2 – May 14

To view the workshop 2 recording, click here.

To view the workshop 2 executive summary click here.

We’re accepting feedback through June 5 in the comments section below.

To participate in the poll questions demonstrated in the workshop recording, take the survey below.

Join Us for Workshop #3 – September 22 at 5 p.m.

Pre-register for the event by clicking the link below.

  • After clicking the link, click the Register button.
  • Enter your name, email and ZIP Code. This information is only used to identify you as an attendee, and to send any follow-up information regarding the workshop.
  • OPPD will email you a link and calendar invite from Cisco Webex on behalf of Kim Barnes

REGISTER HERE

Stay Informed

To receive email updates on upcoming ISP workshops, please add your email to the "Stay Informed" widget at the bottom of this page.

OPPD's Integrated System Plan (ISP) is a vital step in our continual planning process to guide us as we make long-term system plans.

Like most utilities, OPPD engages in ongoing system planning, with an intentional focus on publishing an update to our resource and system strategies every five years. The update also meets a regulatory requirement set by Western Area Power Administration (WAPA) as part of a long-term contract to receive hydroelectric power.

In early 2026, OPPD will begin its ISP engagement process, with a final report submitted to WAPA by the end of the year. This planning process is important to ensure we are ready to support growth and maintain reliability for our customer-owners and the ISP guides how we optimize our energy portfolio and measure potential additions over time.

The last time we submitted an Integrated Resource Plan to WAPA was in 2021. The planning process will differ slightly this time because OPPD will take a broader look at overall system needs, rather than just resource needs. This expanded view will allow OPPD to evaluate generation options in conjunction with related grid infrastructure and customer solutions, including the cost of potential grid buildout and modernizations and other factors in evaluating long-term options.

Long-term, taking an integrated systems approach to planning may uncover grid or customer solutions that can help with generation needs and vice versa which will help optimize the overall planning process.

The study also looks at how our resources actually are being used. In addition to traditional models that forecast the economic dispatch of generating units on the basis of cost only, a system plan will consider the current and future generation required for grid support and system reliability. This creates a modeled portfolio that performs much closer to real-world operations and captures the full range of costs and values.

Workshop #1 - March 24

To view the workshop 1 recording, click here.

To view the workshop 1 executive summary, click here.

We accepted feedback through April 23.

Workshop #2 – May 14

To view the workshop 2 recording, click here.

To view the workshop 2 executive summary click here.

We’re accepting feedback through June 5 in the comments section below.

To participate in the poll questions demonstrated in the workshop recording, take the survey below.

Join Us for Workshop #3 – September 22 at 5 p.m.

Pre-register for the event by clicking the link below.

  • After clicking the link, click the Register button.
  • Enter your name, email and ZIP Code. This information is only used to identify you as an attendee, and to send any follow-up information regarding the workshop.
  • OPPD will email you a link and calendar invite from Cisco Webex on behalf of Kim Barnes

REGISTER HERE

Stay Informed

To receive email updates on upcoming ISP workshops, please add your email to the "Stay Informed" widget at the bottom of this page.

Public feedback on the Integrated System Plan

This tab is for Guestbook Comments only, which will be routed to the project team. If you prefer to leave a Comment without registering on this site, please use this form.

Please see the Questions tab for questions requiring a reply. 

Your input matters. Prior to June 5, we'd like your feedback on the inputs and assumptions to be used in selecting the best portfolio. Resource technology and future scenarios input will be used for future modeling. See slides 38-43 from Workshop 2.

CLOSED: Feedback on Workshop 2 was accepted through June 5.

Public Feedback will be posted here.

OPPD Engagement Team 3 months ago