February 2023 Update

Construction progresses during the winter months with erection of the engine hall in the power block area and with erection of vertical bus supports in the substation area at Standing Bear Lake Station.

The large temporary tent structure at the north of the site has been removed following assembly of the nine Wärtsilä engines. The associated generators have also been received. All three Generator Step-up Transformers (GSU) have been transported to the Standing Bear Lake Station site and are on their foundations.