September 2025 Update

OPPD has moved through much of the required commissioning efforts at Standing Bear Lake Station, including a variety of testing ranging from electrical generator testing to noise and thermal performance testing.

The team is currently working through punch list tasks with our contractor as well as a few plant modifications required prior to substantial completion of the site.

Share September 2025 Update on Facebook Share September 2025 Update on Twitter Share September 2025 Update on Linkedin Email September 2025 Update link