Summer 2022 Update

OPPD's vendor, Zachry Group, continues to prepare laydown and storage areas for equipment, materials, and supplies in anticipation of approaching construction work.

Preliminary grading is winding down and foundation work has begun in preparation for the new facility.

This summer, construction activities will include work on gas and transmission infrastructure, although major equipment isn’t expected to arrive until late summer or early fall.