North Douglas County Transmission Project

Share North Douglas County Transmission Project on Facebook Share North Douglas County Transmission Project on X (formerly Twitter) Share North Douglas County Transmission Project on Linkedin Email North Douglas County Transmission Project link

For the latest construction updates, please see the News Feed at the bottom of this page.


About the North Douglas County Transmission Project

Electrical infrastructure improvements are needed in north Douglas County to accommodate the growing demand for electricity across all customer categories. OPPD must increase transmission capacity to support additional sources of power generation, future enhancements and to maintain reliability. The new infrastructure supports the long-range planning of OPPD’s balanced portfolio of energy-generation resources.

OPPD is constructing, expanding and rebuilding its transmission network in north Douglas County in three segments:

Segment 1

Building a new, 2.3-mile, double-circuit transmission line between 114th and 140th & State streets.

Segment 2

Rebuilding an existing, double-circuit transmission line between 101st & State and 60th & Garvin streets.

Segment 3

Rebuilding an existing, double-circuit transmission line along Interstate 680 from 108th & Blondo to 101st & State streets.


Open House and Online Project Presentation

As part of our public power promise, Omaha Public Power District (OPPD) is committed to informing, educating and engaging customers on projects and key business decisions. OPPD held an open house on Oct. 24, 2024, about this upcoming transmission work.

Online Project Presentation

For those who could not attend in-person Open House event, OPPD hosted an online project presentation Monday, October 28, 2024 at 6 p.m. Missed the presentation? You can view it here.

Following this initial project meeting and open house, land management agents will contact all directly impacted landowners.


Infrastructure

To meet modern standards, the older, lattice-style towers will be replaced with steel monopoles. More monopoles may be added to rebuilt segments, ranging in height from 160 to 190 feet.

Example of older, lattice-style towers
Example of modern steel monopoles


Transmission projects of this scale take years of planning and design. Keeping that in mind, OPPD has a target date of 2027 for completion.

For the latest construction updates, please see the News Feed at the bottom of this page.


About the North Douglas County Transmission Project

Electrical infrastructure improvements are needed in north Douglas County to accommodate the growing demand for electricity across all customer categories. OPPD must increase transmission capacity to support additional sources of power generation, future enhancements and to maintain reliability. The new infrastructure supports the long-range planning of OPPD’s balanced portfolio of energy-generation resources.

OPPD is constructing, expanding and rebuilding its transmission network in north Douglas County in three segments:

Segment 1

Building a new, 2.3-mile, double-circuit transmission line between 114th and 140th & State streets.

Segment 2

Rebuilding an existing, double-circuit transmission line between 101st & State and 60th & Garvin streets.

Segment 3

Rebuilding an existing, double-circuit transmission line along Interstate 680 from 108th & Blondo to 101st & State streets.


Open House and Online Project Presentation

As part of our public power promise, Omaha Public Power District (OPPD) is committed to informing, educating and engaging customers on projects and key business decisions. OPPD held an open house on Oct. 24, 2024, about this upcoming transmission work.

Online Project Presentation

For those who could not attend in-person Open House event, OPPD hosted an online project presentation Monday, October 28, 2024 at 6 p.m. Missed the presentation? You can view it here.

Following this initial project meeting and open house, land management agents will contact all directly impacted landowners.


Infrastructure

To meet modern standards, the older, lattice-style towers will be replaced with steel monopoles. More monopoles may be added to rebuilt segments, ranging in height from 160 to 190 feet.

Example of older, lattice-style towers
Example of modern steel monopoles


Transmission projects of this scale take years of planning and design. Keeping that in mind, OPPD has a target date of 2027 for completion.

  • November 6 Update: Segment 3

    Share November 6 Update: Segment 3 on Facebook Share November 6 Update: Segment 3 on X (formerly Twitter) Share November 6 Update: Segment 3 on Linkedin Email November 6 Update: Segment 3 link

    Construction efforts continue on Segment 3 of the North Douglas County Transmission Project. Please be aware of several road impacts in the area over the next several weeks.

    Road restrictions are expected on Military and Blair High Road during daytime hours Monday through Friday, 11/9/2026 through 11/13/2026. There will be no restrictions in this area on Saturday and Sunday. Restrictions will resume on Monday, 11/16/2026 through Friday, 11/20/2026, on Blair High, Military, and Irvington Roads. All work will be performed during daytime hours between 9am -3:30pm.

    From Nov. 22 – Nov. 24, nighttime closures may be in effect on Sprague Street and Maple’s Northbound onramp to I-680, so please use caution.

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

    Construction efforts continue on Segment 3 of the North Douglas County Transmission Project. Please be aware of several road impacts in the area over the next several weeks.

    Road restrictions are expected on Military and Blair High Road during daytime hours Monday through Friday, 11/9/2026 through 11/13/2026. There will be no restrictions in this area on Saturday and Sunday. Restrictions will resume on Monday, 11/16/2026 through Friday, 11/20/2026, on Blair High, Military, and Irvington Roads. All work will be performed during daytime hours between 9am -3:30pm.

    From Nov. 22 – Nov. 24, nighttime closures may be in effect on Sprague Street and Maple’s Northbound onramp to I-680, so please use caution.

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

  • November Update - Segment 3

    Share November Update - Segment 3 on Facebook Share November Update - Segment 3 on X (formerly Twitter) Share November Update - Segment 3 on Linkedin Email November Update - Segment 3 link

    Progress continues on the construction of segment 3 of the North Douglas County Transmission project. As part of this work, the team begins to install the overhead transmission wires, so there will be a need to temporarily close Interstate 680 overnight on Sunday, November 1. The following week through Nov. 5, night work will continue on and near Interstate 680. We do not anticipate additional road closures, however, lane restrictions and traffic control is expected.

    To reduce impacts on daytime traffic, all work will take place between 10 p.m. and 5 a.m. Construction activities may require temporary lane closures or brief traffic stoppages to provide a safe work area for crews. Traffic control or signed detours will be in place when necessary to safely route traffic around active work areas.

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

    Progress continues on the construction of segment 3 of the North Douglas County Transmission project. As part of this work, the team begins to install the overhead transmission wires, so there will be a need to temporarily close Interstate 680 overnight on Sunday, November 1. The following week through Nov. 5, night work will continue on and near Interstate 680. We do not anticipate additional road closures, however, lane restrictions and traffic control is expected.

    To reduce impacts on daytime traffic, all work will take place between 10 p.m. and 5 a.m. Construction activities may require temporary lane closures or brief traffic stoppages to provide a safe work area for crews. Traffic control or signed detours will be in place when necessary to safely route traffic around active work areas.

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

  • August Update - Segments 2 and 3

    Share August Update - Segments 2 and 3 on Facebook Share August Update - Segments 2 and 3 on X (formerly Twitter) Share August Update - Segments 2 and 3 on Linkedin Email August Update - Segments 2 and 3 link

    Progress continues along Segment 2. OPPD's distribution contractor, Watts, is wrapping up efforts in the western section.

    Transmission construction is underway on Segment 3. In addition to structure wreck-out and wire removal, crews were busy constructing a transmission pole foundation near I-680 and Maple St. The foundation has the largest diameter in OPPD's service territory at 14 feet wide and 68 feet deep. It will support the largest style of transmission structure in OPPD's service territory. The structure needs to be so robust because it supports two spans of more than 1,000 feet where the conductor crosses both I-680 and Maple St.

    Progress continues along Segment 2. OPPD's distribution contractor, Watts, is wrapping up efforts in the western section.

    Transmission construction is underway on Segment 3. In addition to structure wreck-out and wire removal, crews were busy constructing a transmission pole foundation near I-680 and Maple St. The foundation has the largest diameter in OPPD's service territory at 14 feet wide and 68 feet deep. It will support the largest style of transmission structure in OPPD's service territory. The structure needs to be so robust because it supports two spans of more than 1,000 feet where the conductor crosses both I-680 and Maple St.

  • July 31 Update – Segment 3

    Share July 31 Update – Segment 3 on Facebook Share July 31 Update – Segment 3 on X (formerly Twitter) Share July 31 Update – Segment 3 on Linkedin Email July 31 Update – Segment 3 link

    Construction continues to progress along Segment 3 of the North Douglas County Transmission Project. Crews are preparing the transmission corridor, which includes the removal of the old transmission structures and wires. As part of this work, there will be overnight traffic impacts on and near Interstate 680 during two periods in early August as crews remove overhead electric transmission lines at multiple roadway crossings.

    To reduce impacts on daytime traffic, all work will take place between 10 p.m. and 5 a.m. Construction activities will require temporary lane closures, brief traffic stoppages and occasional ramp closures to provide a safe work area for crews removing the transmission lines. Signed detours will be in place when necessary to safely route traffic around active work areas.

    Construction Schedule*

    August 2–3

    • Interstate 680

    • Fort Street

    • Sprague Street

    August 5-7 and 9-10

    • Interstate 680

    • Maple Street (Nebraska Highway 64) 

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

    Construction continues to progress along Segment 3 of the North Douglas County Transmission Project. Crews are preparing the transmission corridor, which includes the removal of the old transmission structures and wires. As part of this work, there will be overnight traffic impacts on and near Interstate 680 during two periods in early August as crews remove overhead electric transmission lines at multiple roadway crossings.

    To reduce impacts on daytime traffic, all work will take place between 10 p.m. and 5 a.m. Construction activities will require temporary lane closures, brief traffic stoppages and occasional ramp closures to provide a safe work area for crews removing the transmission lines. Signed detours will be in place when necessary to safely route traffic around active work areas.

    Construction Schedule*

    August 2–3

    • Interstate 680

    • Fort Street

    • Sprague Street

    August 5-7 and 9-10

    • Interstate 680

    • Maple Street (Nebraska Highway 64) 

    When detours are necessary, motorists may be directed to alternate routes. Motorists are encouraged to allow extra travel time, follow posted traffic control devices and directions from law enforcement and traffic control workers, and reduce speeds when traveling through work zones.

    OPPD appreciates the public's patience and cooperation as crews complete this important infrastructure improvement.

    *Please note, timing is subject to change based on weather or construction conditions. 

  • June 2026 Update - Segment 2

    Share June 2026 Update - Segment 2 on Facebook Share June 2026 Update - Segment 2 on X (formerly Twitter) Share June 2026 Update - Segment 2 on Linkedin Email June 2026 Update - Segment 2 link

    OPPD is relocating distribution lines along Segment 2 of the North Douglas County Transmission Project. This work is expected to continue through the end of October.

    Distribution lines are smaller than the large transmission lines, which will be replaced later. Most of this work will consist of moving existing above-ground distribution lines underground and reconfiguring the equipment on existing above-ground pole structures.

    This work is necessary to move forward with our larger transmission line rebuild project and will improve the resilience and reliability of the electrical grid in the areas where the work is taking place. OPPD's right-of-way agents will reach out to directly impacted property owners with more detailed dates and times for construction at individual properties.

    When relocation of distribution lines in the area begins, you may see crews drilling and boring routes along property boundaries, installing new pad-mounted electrical equipment, and altering the configuration of existing above-ground distribution poles. Our contractors may use trucks, drills, boring rigs, excavators, loaders and lifting equipment to install the new lines.

    Contractors that you may see working with OPPD include:

    Upon completion in October, OPPD and our contractors will perform cleanup, some property restoration and energize the lines. Please note that OPPD and its contractors may need to maintain access to directly impacted properties until the separate transmission line replacement portion of the project is fully completed in May 2027.

    OPPD is relocating distribution lines along Segment 2 of the North Douglas County Transmission Project. This work is expected to continue through the end of October.

    Distribution lines are smaller than the large transmission lines, which will be replaced later. Most of this work will consist of moving existing above-ground distribution lines underground and reconfiguring the equipment on existing above-ground pole structures.

    This work is necessary to move forward with our larger transmission line rebuild project and will improve the resilience and reliability of the electrical grid in the areas where the work is taking place. OPPD's right-of-way agents will reach out to directly impacted property owners with more detailed dates and times for construction at individual properties.

    When relocation of distribution lines in the area begins, you may see crews drilling and boring routes along property boundaries, installing new pad-mounted electrical equipment, and altering the configuration of existing above-ground distribution poles. Our contractors may use trucks, drills, boring rigs, excavators, loaders and lifting equipment to install the new lines.

    Contractors that you may see working with OPPD include:

    Upon completion in October, OPPD and our contractors will perform cleanup, some property restoration and energize the lines. Please note that OPPD and its contractors may need to maintain access to directly impacted properties until the separate transmission line replacement portion of the project is fully completed in May 2027.

  • June 2026 Update - Segment 1 and 3

    Share June 2026 Update - Segment 1 and 3 on Facebook Share June 2026 Update - Segment 1 and 3 on X (formerly Twitter) Share June 2026 Update - Segment 1 and 3 on Linkedin Email June 2026 Update - Segment 1 and 3 link

    Construction on Segment 1 is now complete.

    Construction is expected to begin after the July 4th holiday on Segment 3. Although we've been working on the smaller distribution lines and tree clearing in the area, this construction will include installing new foundations, poles and high voltage transmission lines.

    This work will take place at various times. Still, you will see OPPD and our contractors, Brink Constructors and Dietzel Enterprises, as work progresses. 

    We recognize this work may cause some inconvenience, and we appreciate your patience and understanding as we work to improve our infrastructure. Safety is a priority. We’re asking our neighbors to be aware of construction activities around their property and to avoid entering active work sites. It’s essential to allow sufficient space for field crews and their equipment.

    Construction on Segment 1 is now complete.

    Construction is expected to begin after the July 4th holiday on Segment 3. Although we've been working on the smaller distribution lines and tree clearing in the area, this construction will include installing new foundations, poles and high voltage transmission lines.

    This work will take place at various times. Still, you will see OPPD and our contractors, Brink Constructors and Dietzel Enterprises, as work progresses. 

    We recognize this work may cause some inconvenience, and we appreciate your patience and understanding as we work to improve our infrastructure. Safety is a priority. We’re asking our neighbors to be aware of construction activities around their property and to avoid entering active work sites. It’s essential to allow sufficient space for field crews and their equipment.

  • March 2026 Update: Segment 3

    Share March 2026 Update: Segment 3 on Facebook Share March 2026 Update: Segment 3 on X (formerly Twitter) Share March 2026 Update: Segment 3 on Linkedin Email March 2026 Update: Segment 3 link

    OPPD is finishing the tree removal process and will soon begin the distribution line relocation phase of Segment 3 of the North Douglas County Transmission Project. We anticipate beginning the relocation of distribution lines in early March and finishing in April. Note that these are smaller than the large transmission lines which will be replaced later. Most of this work will consist of placing existing above-ground distribution lines underground and reconfiguring the equipment on existing above-ground pole structures.

    This work is necessary to move forward with our larger transmission line upgrade project and will improve the resilience and reliability of the electrical grid in the areas where the work is taking place. OPPD's right-of-way agents will reach out to directly impacted property owners with more detailed dates and times when construction will be happening at individual properties.

    When installation of the new underground distribution lines begins, you may see crews drilling and boring routes along property boundaries, installing new pad-mounted electrical equipment, and altering the configuration of existing above-ground distribution poles. Our contractors may use trucks, drills, boring rigs, excavators, loaders and lifting equipment to install the new lines.

    Contractors that you may see working with OPPD include:

    We anticipate the distribution line portion of construction in the area to be completed by the end of April 2026. Upon completion, OPPD and our contractors will perform cleanup, some property restoration and energize the line. Please note that OPPD and its contractors may need to maintain access to directly impacted properties until the separate transmission line replacement portion of the project is fully completed later in 2026.

    OPPD is finishing the tree removal process and will soon begin the distribution line relocation phase of Segment 3 of the North Douglas County Transmission Project. We anticipate beginning the relocation of distribution lines in early March and finishing in April. Note that these are smaller than the large transmission lines which will be replaced later. Most of this work will consist of placing existing above-ground distribution lines underground and reconfiguring the equipment on existing above-ground pole structures.

    This work is necessary to move forward with our larger transmission line upgrade project and will improve the resilience and reliability of the electrical grid in the areas where the work is taking place. OPPD's right-of-way agents will reach out to directly impacted property owners with more detailed dates and times when construction will be happening at individual properties.

    When installation of the new underground distribution lines begins, you may see crews drilling and boring routes along property boundaries, installing new pad-mounted electrical equipment, and altering the configuration of existing above-ground distribution poles. Our contractors may use trucks, drills, boring rigs, excavators, loaders and lifting equipment to install the new lines.

    Contractors that you may see working with OPPD include:

    We anticipate the distribution line portion of construction in the area to be completed by the end of April 2026. Upon completion, OPPD and our contractors will perform cleanup, some property restoration and energize the line. Please note that OPPD and its contractors may need to maintain access to directly impacted properties until the separate transmission line replacement portion of the project is fully completed later in 2026.

  • February 2026 Update: Segment 2

    Share February 2026 Update: Segment 2 on Facebook Share February 2026 Update: Segment 2 on X (formerly Twitter) Share February 2026 Update: Segment 2 on Linkedin Email February 2026 Update: Segment 2 link

    OPPD is in the pre-construction stage for the North Douglas County Transmission Project, and crews will continue clearing trees and brush from the transmission line easement areas as they prepare the transmission corridor along Segment 2. This work will occur at various times. You will continue to see OPPD and our contractor – Hughes Tree Service and Asplundh – as work progresses.

    Safety is a priority. We kindly ask you to be aware of activities happening around you. Please do not enter active worksites and allow plenty of space for field crews and equipment. Thank you for your patience as we make these investments to support reliability and growth across the district.

    OPPD is in the pre-construction stage for the North Douglas County Transmission Project, and crews will continue clearing trees and brush from the transmission line easement areas as they prepare the transmission corridor along Segment 2. This work will occur at various times. You will continue to see OPPD and our contractor – Hughes Tree Service and Asplundh – as work progresses.

    Safety is a priority. We kindly ask you to be aware of activities happening around you. Please do not enter active worksites and allow plenty of space for field crews and equipment. Thank you for your patience as we make these investments to support reliability and growth across the district.

  • Jan 2026 Update: Segment 1

    Share Jan 2026 Update: Segment 1 on Facebook Share Jan 2026 Update: Segment 1 on X (formerly Twitter) Share Jan 2026 Update: Segment 1 on Linkedin Email Jan 2026 Update: Segment 1 link

    Construction on Segment 1 of OPPD’s North Douglas County Transmission Project is scheduled to begin Jan. 26.

    Crews will begin building the transmission line along State Street, between 114th and 140th streets. Construction includes installing new foundations, poles and high-voltage transmission lines. OPPD has already relocated smaller distribution lines in the area. OPPD anticipates completing this segment in June 2026.

    This work will take place at various times. Still, you will see OPPD and our contractors, Brink Constructors and Dietzel Enterprises, as work progresses. 

    We recognize this work may cause some inconvenience, and we appreciate your patience and understanding as we work to improve our infrastructure. Safety is a priority. We’re asking our neighbors to be aware of construction activities around their property and to avoid entering active work sites. It’s essential to allow sufficient space for field crews and their equipment.

    Construction on Segment 1 of OPPD’s North Douglas County Transmission Project is scheduled to begin Jan. 26.

    Crews will begin building the transmission line along State Street, between 114th and 140th streets. Construction includes installing new foundations, poles and high-voltage transmission lines. OPPD has already relocated smaller distribution lines in the area. OPPD anticipates completing this segment in June 2026.

    This work will take place at various times. Still, you will see OPPD and our contractors, Brink Constructors and Dietzel Enterprises, as work progresses. 

    We recognize this work may cause some inconvenience, and we appreciate your patience and understanding as we work to improve our infrastructure. Safety is a priority. We’re asking our neighbors to be aware of construction activities around their property and to avoid entering active work sites. It’s essential to allow sufficient space for field crews and their equipment.

  • Jan. 2026 Update: Segment 3

    Share Jan. 2026 Update: Segment 3 on Facebook Share Jan. 2026 Update: Segment 3 on X (formerly Twitter) Share Jan. 2026 Update: Segment 3 on Linkedin Email Jan. 2026 Update: Segment 3 link

    OPPD is moving into the pre-construction stage for the North Douglas County Transmission Project, which will improve the electric transmission network to serve increasing demand by all customers. In this next stage, crews will begin preparing the transmission corridor along Segment 3. Crews will begin to remove trees and brush in the Sunny Slope neighborhood beginning on January 12. This work will occur at various times. You will continue to see OPPD and our contractor – Hughes Tree Service and Asplundh – as work progresses.

    Safety is a priority. We kindly ask you to be aware of activities happening around you. Please do not enter active worksites and allow plenty of space for field crews and equipment. Thank you for your patience as we make these investments to support reliability and growth across the district.

    OPPD is moving into the pre-construction stage for the North Douglas County Transmission Project, which will improve the electric transmission network to serve increasing demand by all customers. In this next stage, crews will begin preparing the transmission corridor along Segment 3. Crews will begin to remove trees and brush in the Sunny Slope neighborhood beginning on January 12. This work will occur at various times. You will continue to see OPPD and our contractor – Hughes Tree Service and Asplundh – as work progresses.

    Safety is a priority. We kindly ask you to be aware of activities happening around you. Please do not enter active worksites and allow plenty of space for field crews and equipment. Thank you for your patience as we make these investments to support reliability and growth across the district.